concrete slab scheduled depth
P1 | 8"8 in
Local vertical section thickness only. No top or bottom world elevation follows from this value.
Drawing notation: PLAN; P1 (page-left lower slab field); DETAILS OF FRAMING FOR FRONT ENTRANCE STEPS
P1 is a printed slab mark; page-left is a photographic position, not an east/west assignment. The perimeter of this P1 field has not been independently picked or dimensioned.
Drawing notation: CONCRETE SLAB SCHEDULE; MARK P1; DEPTH 8"
The P1 schedule row governs slab depth. Rod and spacer figures were not transcribed in this bounded pass.